• Cobbydaler (edited 9 years ago)
    +5

    The associated link I just posted says (for the assembly) 1,300 people for 10-11 18 hour (2 shift) days. So that's 234,000 man hours for assembly! The entire build takes 10-12 months but it doesn't say how many people are involved. Edit - that may be 1,300 people across the two shifts, if so that's 'only' 117,000 man hours.

    • Splitfish
      +3

      Just astonishing. Can you imagine one person trying to do all that! I don't think there is enough time in a lifetime.

      • Cobbydaler
        +3

        117,000 hours is about 40 years of 8 hour days if you worked 7 days a week. About 56 years if you worked 5 day weeks.